Project information and notifications of upcoming work will be posted on this page throughout construction of the new Steveston Interchange.
General Updates
- We selected Flatiron Constructors Canada Limited (Flatiron) to design and build the Steveston Interchange Project in March 2022.
- Flatiron spent most of 2022 completing preliminary work for the project (including site set-up, geotechnical, soil and utility investigations) and preparations (including removing trees, vegetation and topsoil) for major construction starting in 2023.
- We provide advance notice to surrounding community members on our construction activities. These are posted below in the “Construction & Traffic Updates” section.
Construction & Traffic Updates
Telus crews will remove poles north of the Steveston Interchange Project between March 20-22. There will be a full closure on Highway 99 and lane closures on Steveston Highway.
There will be a two-hour overnight closure on Highway 99 on March 5-6 while crews finish the relocation of an existing BC Hydro electrical line north of the Steveston Interchange Project.
On February 13, crews will begin tree removal for construction of the Steveston Interchange Project. The work will take place on the east and west sides of the interchange along Steveston Highway and last about three weeks.
Starting January 16 and lasting for about a month, crews will install a new electrical line across Highway 99. This work includes installing new wooden electrical poles adjacent to Steveston Highway and Highway 99 ramps, connecting the new line to an existing line on both sides of Highway 99, and removing the existing poles and line.
As part of the Province of B.C.’s Steveston Interchange Project, which will expand the interchange from two to five lanes, crews are preparing the area for the new interchange construction. Starting on November 3 and lasting for approximately three months, crews will remove trees, vegetation, and topsoil within the vicinity of the Steveston Interchange, including the northbound onramp onto Highway 99, in advance of upcoming utility relocation work. Crews will also build access roads into the construction area at the same time.
As part of the Province of B.C.’s Steveston Interchange Project, which will expand the interchange from two to five lanes, crews will perform soil sampling and electrical work. Traffic impacts are not anticipated, and noise impacts will be minimal.
As part of the Province of B.C.’s Steveston Interchange Project, which will expand the interchange from two to five lanes, crews will set up a temporary office facility on the west side of Highway 99 within the Province’s right-of-way. There will be trucks and equipment involved in the set up, but there will be no traffic impacts.
As part of the Province of B.C.’s Steveston Interchange Project, which will expand the interchange from two to five lanes, crews will be performing utilities investigation in the project area. This work involves using a hydrovac truck to remove the asphalt and soil to locate utilities. Crews will work in the shoulder area of eastbound Steveston Highway by Richmond Country Farms. Work will be completed overnight to minimize traffic impacts on Highway 99.
As part of the Province of B.C.’s Steveston Interchange Project, which will expand the interchange from two to five lanes, crews are completing geotechnical investigations in the project area. Geotechnical investigations involve drilling boreholes to gather important information about soil conditions. Crews will work in the areas surrounding the loop on-ramp on the east side of the interchange. This work will require a hydrovac truck and truck-mounted drill rig equipment. Work will be completed overnight to minimize traffic impacts on Highway 99.
As part of the Province of B.C.’s Steveston Interchange Project, which will expand the interchange from two to five lanes, crews will continue geotechnical investigations in the project area. Geotechnical investigations involve drilling boreholes to gather important information about soil conditions. Crews will work in the areas surrounding the Highway 99 southbound HOV/bus lane, Highway 99 eastbound to northbound on-ramp, and near the bridge approaches on Steveston Highway. This work will require a hydrovac truck and track-mounted drill rig equipment. Work will be completed overnight to minimize traffic impacts on Highway 99 and Steveston Highway.