Highway 99 and 17A Off-Ramp Widening

Extension and widening of the northbound Highway 99 off-ramp approach to the Highway 17A intersection, upgraded George Massey Tunnel bike shuttle stop and improvements to cycling facilities in and around the interchange. Construction is anticipated to start in March 2022, with project completion in September 2022.

Contracts have been awarded for all three Transit and Cycling Improvement Project components, and further information on the contracts can be found here.

  • Schedule: Construction is anticipated to start in March 2022, with project completion in Fall 2022.
  • Status: Contract awarded to Lafarge Canada Inc. of Port Coquitlam for Bridgeport Road Bus Construction project and Highway 99 and 17A Off-Ramp Widening.
  • Project Cost: $5.28 million (for both Highway 99 and 17A Off-Ramp Widening and Bridgeport Road Bus Connection).